Fictional completed example · Scenario MS-031
spectra
Sign-job operating kit
Installation handover · Pilot example

Installation handover record

A worked pilot-site handover for a fictional four-site rollout. It distinguishes installed scope, exceptions and owner actions.

Fictional completed example

Scenario MS-031 · Juniper Dental (fictional). This is an instructional fixture, not customer work, certification or evidence that the remaining sites are released.

Pilot completion

Site 1 of 4 · 20 October 2026
ItemCompleted exampleEvidence / state
Installed scopeOne external fascia face and two internal direction panelsPhotos PILOT-01 to PILOT-06 · complete
Proof / versionMaster artwork v4; site adaptation S1-v2Matched installation pack · checked
Visual checkIdentity, orientation and visible finish reviewed from agreed positionsInstaller record · complete
Site conditionWork area cleared; packaging removedHandover photo · complete
Customer acknowledgementVisible installed scope received; exceptions remain separately openFictional acknowledgement REF-MS031-P1

Exceptions and rollout decision

Owner action required
TypeRecordOwnerNext step
ExceptionReception panel fixing position moved 40 mm to avoid an observed service routeTechnical ownerUpdate site adaptation notes before reuse
UnknownLandlord access windows for sites 2–4Customer contactConfirm before scheduling
AssumptionPilot colour reference becomes the rollout reference only after written acceptanceArtwork ownerObtain acceptance and lock version
DecisionRemaining sites are not released by this handoverJob ownerClose pilot review first