Sign-job operating kit
Estimate worksheet · Example v2

Versioned estimate worksheet

A synthetic illuminated-fascia calculation that keeps evidence, assumptions and revision triggers visible.

Fictional completed example

Scenario IF-118 · North Pier Cycles (fictional). These are synthetic teaching inputs, not market rates, a rate card, a supplier quotation or pricing guidance. Tax, approved terms and final rounding are not included.

Estimate basis

Version 2 · review only
LineSynthetic evidence / formulaAmount
MaterialsIllustrative supplier evidence dated 2026-09-20£720.00
Illumination componentsIllustrative bought-in input£280.00
Workshop labour20 hours × £38 fictional internal input£760.00
Installation / travelRevised after the fictional access survey£780.00
Direct costSum of lines above£2,540.00
Internal allocation12% fictional method × direct cost£304.80
Cost baseDirect cost + allocation£2,844.80
Selling basis£2,844.80 ÷ (1 − 32% fictional gross-margin target)£4,183.53

Revision and controls

Owner trail
ControlCompleted exampleOwner
Revision triggerAccess method changed after survey; v1 retained as supersededEstimator
UnknownExisting electrical condition; any remedial work remains excludedInstall coordinator
AssumptionOne installation visit during agreed site hoursAccount lead
Release stateCommercial review only; not production instructionCommercial owner

Revision note: version 1 used £460 for installation/travel and 18 workshop hours, producing a £3,531.29 selling basis. Version 2 records the changed access assumption, £780 installation/travel and 20 hours; version 1 remains superseded. Gross margin uses gross profit ÷ selling price and this fictional target is not a recommendation.